That is really a hard question to answer. It can take anything from 1 week to 3 months. It all depends on many factors including:
How many vehicles are available for use
How many cycles per vehicle
Authority Testing (TUV / CSEI)
Mandated fault free cycle testing (CSEI is 80 hours no fault)
How many brake runs as this helps distinguish how many zones
If its a small coaster, you could be done in 2 weeks. If its a large dark ride it could take 4 months.
So yeah - not an easy answer.
Just wondering if anyone has any updates with regard to testing of the 3 new coasters, I believe they started earlier this month. Does anyone know how long testing normally takes on these types of coasters?
When are the new roller coasters in Motiongate going to open? I am planning to visit.
Only photos I could capture of the other new coaster at Motiongate
Photos of the new coaster from behind the park
We are planning to stay over Christmas so I e-mailed the park regarding the opening of the new rides at Motiongate and Bollywood and they replied that there is no fixed date yet but hoping for the end of November to early December. It's certainly good to hear that testing has began as they seem to have been finished and sitting dormant for a few months now.
It would be interesting to hear what's happening with the Riverland area as it would seem most restaurants have shut. I'm a bit worried about the whole area. The Legoland Hotel seems finished but dormant, they just cannot seem to get the numbers through the gates. Such a shame as we visited a couple of years back and it's all very impressive.
I saw the tests of the 2 coaster of Motiongate. The decor company has finished its work. It is scheduled to open in November