1. Investment entailed by the park.
IMGWOA is largely funded by the promoters, Ilyas Galadari and Mustafa
Galadari, IMG’s Executive Co-Chairmen, with some strategic financial
investment from two local banks, Al Hilal Bank and Mashreq Banks.
2. Percentage completion of the project?
The work is progressing on two fronts; the Onsite construction and the
off-site ride manufacturing.
Onsite construction works is progressing significantly with structural
columns and space frame being installed. In the coming ten weeks,
significant portion of the steel structure enclosing the entire facility
will be completed.
Off-site ride manufacturing, at various vendor sites, is currently being
done simultaneously for shipment planned in the later part of this year.