It's a busy time right now at the waterpark - lots of landscaping is going in, supports for the water coaster are being installed, and waterslides continue to test!
Meanwhile at the adjacent theme park not much is happening yet but hopefully that will change next year...
Sources: https://v.douyin.com/JD67qbE/ and https://v.douyin.com/JDKnrXo/ and https://v.douyin.com/JUAvFgF/ and https://v.douyin.com/JU5a8c8/ and https://v.douyin.com/JyBhnU1/ and https://v.douyin.com/JyBQBEK/ and https://v.douyin.com/JyBubJh/ and https://v.douyin.com/Jyuoexf/
Sources: https://m.weibo.cn/status/4552258014939366 and https://v.douyin.com/JAqJ5Yy/ and https://v.douyin.com/JAqhDwd/ and https://v.douyin.com/JAVEtea/ and https://v.douyin.com/JAqABGs/ and https://v.douyin.com/JAqhSYY/ and https://v.douyin.com/JAVwaxn/ and https://v.douyin.com/JAqJPs8/ and https://v.douyin.com/JAqAvxs/ and https://v.douyin.com/JAqRfYV/ and https://v.douyin.com/JAq27sd/ and https://v.douyin.com/JAbRo4p/ and and https://mp.weixin.qq.com/s/oRiRVsVcuCR4QcBtzW9tDA and https://mp.weixin.qq.com/s/_aV1i8UJdH9i9xC7EzP5Vw
Waterslide testing has begun!
This is the current schedule for the waterpark, which is expected to open by the end of June 2021:
October 15, 2020 - First batch of waterslides to be tested and pass inspection
December 30, 2020 - Installation of water coaster completed
March 1, 2021 - Lazy river completed
March 30, 2021 - Theming completed
March 30, 2021 - Wave pool completed
March 30, 2021 - Installation of all waterslides completed
April 15, 2021 - Landscaping completed
Source: https://mp.weixin.qq.com/s/pEzQuZInTW6IGTmVo2B6hg
Source: https://v.douyin.com/JStWLch/
New concept art:
Source: https://hz.house.ifeng.com/news/2020_09_11-53167840_0.shtml
Hotel construction progress:
Sources: https://mp.weixin.qq.com/s/NAsOyA3NueRZs6PGsk5i5Q and https://v.douyin.com/JBFxstP/ and https://v.douyin.com/JBFTEAv/