Motiongate Dubai
Views: 1,160,311

Post an Update
Page 35 of 50 First Page ... 31 32 33 34 35 36 37 38 39 ... Last Page
Posts 341 - 350 of 499
Local Name:
موشنجيت دبي
Former Name(s):
Dubai Adventure Studios
Budget:
$750M
Announced:
07 Sep 2014
Construction Start:
Apr 2014
Opening:
18 Dec 2016
Location:
Area:
37 ha
Developer:
  1. I have seen a video yesterday regarding the construction progress of Motiongate. However, it had been deleted and nowhere to be found. It showed that nearly most of Motiongate infrastructure were nearly completed. The DreamWorks building looks done and also the main plaza.

  2. This interview by City7 TV gives you a clear insight in what to expect :
    https://www.youtube.com/watch?v=KmfLl2NxxIw

    From: From beginning to 4:00


  3. Bevy is offline themeparX Top Investigator
    Join Date
    Feb 2015
    Posts
    235
    "China State wins $67m contract to link Dubai Bollywood and Legoland resorts site"

    he regional unit of China State Construction Engineering Corporation (CSCEC) has won a US$67 million contract to build access roads to the forthcoming Dubai Parks and Resorts site.

    The contract from the Dubai Roads and Transport Authority (RTA) will involve the construction of two new ramps to provide access to the site from Sheikh Zayed Road as well as at-grade intersections from the link road between Sheikh Zayed Road and Mohammed bin Rashid Road.
    Read more here:
    http://www.thenational.ae/business/travel-tourism/china-state-wins-67m-contract-to-link-dubai-bollywood-and-legoland-resorts-site

  4. Universal8 is offline Senior Park Investigator
    Join Date
    Jun 2015
    Posts
    13
    Any details on Motiongate's construction progress?

  5. What did the CEO say?

  6. Dubai Parks' CEO speaking:


  7. Bevy is offline themeparX Top Investigator
    Join Date
    Feb 2015
    Posts
    235
    Steady construction progress has been reported at the project; 17% of work on the total development has been conducted, and engineering and manufacturing elements for the rides are 40% complete.

    Infrastructure work is 45% complete at Legoland, where piling activities are currently in progress. Moreover, rides for the theme park are ready to be shipped in from Europe.

    Things are also progressing steadily at Bollywood Parks, with 30% of the projects infrastructure now complete.
    Read more here:
    http://www.constructionweekonline.com/article-33934-roller-coaster-rise/3/


  8. Amazing string of updates! Thanks to all who provided.