Here's a look at the main tower's interior from earlier this month: http://v.youku.com/v_show/id_XMzE1MzIwODM2MA
Send your construction pics to content_at_themeparxdotcom
Here's a look at the main tower's interior from earlier this month: http://v.youku.com/v_show/id_XMzE1MzIwODM2MA
Grand opening is set for April 28, 2017
Source: http://news.sina.com.cn/o/2017-11-19/doc-ifynwnty5141196.shtml
Room reservations and day experience reservations (admission to Aquaventure Waterpark and Lost Chambers Aquarium) can now be made on the Atlantis Sanya website. The first day of availability is May 1, 2018.
Sources: https://www.atlantissanya.com/reservation/day-activities/book-now and http://travel.people.com.cn/n1/2017/1110/c41570-29639021.html
Nice find @Michael, that first video is amazing!!!
Love the themed waterpark with those awesome slides:
![]()
Animals have begun to arrive at the resort's indoor aquarium, as shown in the below photo of beluga whales being transported
Make sure you check out the videos below as well especially the first one it's fantastic:
Construction progress video: https://v.qq.com/x/page/u0565u3lqjv.html
Video from launch event: https://v.qq.com/x/page/c0564kbgtsw.html
Promotional video: https://v.qq.com/x/page/b0565odbzbs.html
Source: http://www.hq.xinhuanet.com/news/2017-10/28/c_1121871217.htm
Big construction update!
Paraphrased/rough translation: "Atlantis Sanya Resort is progressing smoothly. Presently, the main structure of the main resort tower has been completed and the project is scheduled to officially open next year in April. On October 15, the news reporter saw on the project's site that the main building has been capped, curtain wall construction, aquarium of acrylic glass construction and waterproof construction, water park theme packaging and other work have been basically completed. Presently, work is finishing up in the rooms including decorating, mechanical and electrical installation."
Source: http://www.xbxys.com/html/8746552.html
Photo from this month of the main tower and and waterslides at night
Source: https://m.weibo.cn/status/4161287694878046
Interview with the managing director of Atlantis Sanya: https://v.qq.com/x/page/w0550oie6c9.html
It appears that the exterior of the main tower is complete!
Source: https://m.weibo.cn/status/4152185782087703
Source: http://hi.people.com.cn/n2/2017/0907/c231190-30706769.htmlSeptember 6, overlooking the Sanya Atlantis project site, the main structure of the tower and the secondary structure and curtain wall construction has been completed, room decoration, mechanical and electrical commissioning and landscaping is under construction, water park is being installed.
Sanya Atlantis holiday project covers an area of 806 acres, cost about 11 billion yuan. As of the end of August this year, the project has completed 81% of the total investment.