Answers here false. Groundbreaking party in Oct. no investor named? Groundbreaking without permits? Why AWW telling truth now?
http://inparkmagazine.blogspot.co.uk/2011/12/we-pose-some-questions-to-adventure.html
IPM: What are the funding sources for Adventure World Warsaw?
AWW: In line with the investor agreement, this information must stay confidential until we start construction work on AWW. Full financing for the project has been guaranteed by the investor and is conditioned only by providing the building permit, which will be achieved most probably in June 2012. Las Palm has spent over 11 mln euro on the project so far. We believe this amount of financial resource shows our determination and serious intentions to bring the first amusement park in Poland at this scale.
IPM: Is this correct: Groundbreaking in July 2012, opening in 2014?
AWW: Yes, these are the latest dates according to our revised schedule from December 2011. Start of construction has been so far delayed by half a year due to formal issues not depending on Las Palm company, which is leading the project. But together with the Mayor of Grodzisk Mazowiecki, we are successfully overcoming these obstacles, within which the greatest challenges were the land re-zoning and funding of the existing and future roads. We anticipate the various positive decisions to be made between February and July 2012 which will allow us to start the ground works.
IPM: Who owns the land on which AWW will be developed?
AWW: Las Palm has signed preliminary agreements with the private land owners who are mostly farmers. The ownership will be finally moved to Las Palm by purchasing the land next year after the zoning plan is agreed by the local authorities which is anticipated to happen in April 2012.